Chinmaya Mission San Jose
CMSJ New Building Project

A Letter from the CMSJ Board to the members of the Chinmaya Mission Community

Donate Online to the CMSJ New Building Fund

 

New Building Project – Details

 

The Need for a Facility

Chinmaya Vision – A Commitment to Excellence

As Bala Vihar enrollment and attendance at events grows, the Chinmaya vision - “to provide maximum happiness, to the maximum (number of) people, for the maximum time” - continues to inspire the entire Chinmaya Mission San Jose community. In the midst of increasing challenges, our commitment to excellence remains strong as ever. It is quite evident that the present Sandeepany San jose Facility is not adequate to support needs of our activities: Balavihar, Yagnas, Pujas & Festivals. Our need for a new facility emerges from this situation.

New Building Plan & Status

We started the New Building project on Maha Shivarathri in 2006 and acquired the property - an old church - on 10160 Clayton Road in San Jose,  in January 2008 (2 buildings, ~11,000 sq ft total, 1.7 acres) at a cost of $2.6M and are in the process of building a new ashram from the ground up on the property. Architectural plans for the new ashram have been approved by the City of San Jose and we have been granted a Planned Development permit. Construction drawings are being worked on, which will be reviewed by the City and this will culminate in obtaining a Building permit that will help us commence construction.

Current Status ( Updated Nov 14, 2011)

This message is to inform everyone about the status of the new building - prior to the summer break, we had indicated that the architectural design had been completed and approved, we were in the midst of discussions with banks on securing a bank loan, and we were looking forward to the ground breaking ceremony in July in the presence of Pujya Guruji.

As many of you might know, we completed a very auspicious ground breaking ceremony in the presence of Pujya Guruji Swami Tejomayananda in July

Through the summer we have been working closely with the architect, banks and contractors to finalize our building plans but the initial bids came in significantly above the original projected cost. 

In order to keep our projected construction costs under control, based on our guidance, our architect made some minor modifications to the original proposal. We are awaiting the Revised Planned Development (PD) Permit from the city before final construction drawings are completed and submitted for a Building Permit. With final construction plans we expect more accurate bids while we wait for building permit.
In parallel, we're talking to many lenders through a couple of mortagage brokers. Although the banks actually keen to move quickly, but we're proceeding at a pace that is tracking the timing to the city approvals. 

So, in summary, the sequence of events that need to occur before we can start construction are the following:
1. Receiving PD permit from the city
2. Validating that estimated construction bids are in the ball park of our projections 
3. Submitting final construction drawing for a building permit
4. Getting more accurate construction bids based on the final construction bids and, in parallel, securing the bank loan.

With the support of the broad community over the past months and years and with God Grace, Pujya Gurudev's and Pujya Guruji's blessings we expect the construction to begin in Q2 2012 timeframe. So, towards that end, on behalf of CMSJ and our Acharya Br. Prabodhji, some of us will be reaching out to you for your help to raise funds over the next many months.

Floor Plan Lower | Floor Plan Upper | Site Plan Lower | Site Plan Upper

New Building Views

new building 1


new building 2